Management at PROTEA ENERGY has forged strong bonds with Original Equipment Manufacturers (OEM) throughout the world, over their 15 year involvement in the renewable energy arena in Europe. The knowledge gained from these relationships has accumulated in a vast understanding and application of the Project Development Steps stipulated below with approximate time lines:

1. Secure Land Lease

1. Secure Land Lease

Speed at discretion of individual land owner

2. Wind Measurement

2. Wind Measurement

Approximately 1 year

3. Authority Permits

3. Authority Permits

1 to 3 years depending on authorities and complexity of application.

4. Construction

4. Construction

Up to 1 year depending on complexity.

5. Operation

5. Operation

20 Plus years.

6.Ongoing

6.Ongoing

  • Phase 2 if applicable
  • Upgrades
  • Operation & Maintenance